Decommissioning engineers expand into South America

Decommissioning consultancy RVA Group has completed its first assignment in South America, following a two-week financial provisioning exercise for Portugal’s largest electricity giant, EDP.

EDP is no stranger to RVA’s services, having engaged the decommissioning engineers to write the specification for the demolition of the Barreiro power station in Portugal, in 2011.

This project, in the state of Ceará in Brazil, was part of a due diligence report for the Pecém 1 Energia thermal power plant. With a total capacity of 720 megawatts, the plant produces the equivalent of half the electricity generated for the state.

Keen to secure independent expertise regarding the potential future of this 210-acre site, EDP appointed RVA to produce a detailed decommissioning costings study.

2023 01 04 121853

This estimating exercise does not mean that clearance of all – or even part – of the plant is imminent. Instead, RVA’s evidenced data provides EDP with costed options – underpinned by financial integrity – if or when it decides to embark on any decommissioning works moving forward.

This means the fiscal obligation of any future project, is understood and anticipated, therefore minimising the commercial risks for stakeholders.

“As with any project like this, knowledge is power,” commented RVA Group’s managing director Richard Vann. “So, the earlier that decommissioning engineers can become involved in a potential assignment, the greater the quality of any ensuing outputs.”

EDP’s director of decommissioning Bruno Travassos added: “As an organisation, we’re now empowered with information that will support us in future decision-making processes and allow us to better plan the resources and milestones required for any future decommissioning works, large or small.  Such projects are complex and have a large number of variables, so preparation is key.”

Published in Power & water
Tagged under

Specialist decommissioning engineering consultancy RVA Group has launched a new service as the number of industrial and process site closures globally, continues to rise.

Having successfully delivered more than 850 decommissioning, decontamination, demolition and dismantling (DDDD) projects all over the world, the London-headquartered firm has identified a gap in the market when it comes to one of the earliest phases of preparing a site to be mothballed or removed.

2021 06 28 090951

Asset owners commonly use internal resources to handle initial decommissioning works – often due to the fact they don’t consider alternative approaches. However, global industry standards such as the CDM Regulations, state that it is best practice – and the law in the UK – for decommissioning to fall within this remit. A principal designer should therefore be involved from the earliest phase, to ensure the works are rigorously planned from the outset.

So, while the asset owner can assume the role of principal contractor, an experienced team with a decommissioning mindset should be charged with supporting or writing the decommissioning plan itself, as well as documenting the detailed processes to follow, and auditing works throughout. This is the most secure way of ensuring the project unfolds with the highest possible safety and environmental standards, believes RVA Group’s managing director Richard Vann.

“Nobody knows an asset or site better than the operator who has run it for several years,” he explains. “So, when the owner calls time on its operational life it would be unwise to overlook the depth and value of process and plant-specific knowledge that such individuals could bring to the table, during a decommissioning project.

2021 06 28 091011

“However, despite decommissioning often being considered an extension of site maintenance, it represents a specific engineering discipline which requires a distinct mindset. There’s a difference between measures for maintenance or routine turnaround purposes for instance and decommissioning the asset entirely because it has reached its end of life and will never be restarted. Ironically, DDDD presents a number of opportunities that will not only make the process cost effective but also, in many instances, remove hazards and enable increased EHS standards to be implemented.

“Professionals in our industry are often engaged when decommissioning work is already underway, but by that point, avoidable risks may already have been taken and additional measures may be required to rectify decommissioning issues that should have been undertaken by the right people, armed with the right information, at the right time.”

2021 06 28 091031

There’s also a financial argument for earlier involvement from decommissioning specialists, adds Richard.

“Sometimes operators go to such extremes that they undertake processes they don’t actually need to, as they could be handled more efficiently, and ultimately safely, during the dismantling phase,” he highlights. “Such an approach therefore results in abortive effort and cost. Costs will also rise if extra resource is required to get a project back on track – and the monetary consequences of an event, such as loss of containment doesn’t even bear thinking about.”

Having supported clients within the global chemical, petrochemical, pharmaceutical, power, energy, oil, gas and heavy manufacturing industries, RVA’s client roster includes names such as INEOS, SABIC, BASF, Total and GSK – to name just a few.

Established in 1992 and now a part of EPH following a strategic acquisition in 2017, the team brings more than 200 years combined decommissioning experience to the market.